School Projects

Projects by School

Measure D projects will be listed here by school as they are approved by the Board of Trustees, with the scope of work, budget, timeline, current status, and photos or renderings.

Phase 1 Projects (design, fall 2026)

On November 18, 2026, the Board of Trustees approved Phase 1 design contracts for all three schools. All scopes and dates below are preliminary and will change as design advances and the Division of the State Architect (DSA) reviews the plans.

Hall Middle School

  • Summer 2027: fencing, gates, ADA pathways, and painting
  • 2027 or 2028: reroofing and solar, pending DSA review
  • 2028: synthetic turf and field lighting, with lighting infrastructure installed first
  • 2028 or 2029: HVAC cooling, depending on PG&E
  • Environmental review (CEQA) is underway, including the field lighting

Neil Cummins Elementary

  • Perimeter fencing and gates, replacing chain-link
  • Reroofing and new gutters at the Multipurpose Room and Student Services
  • Solar panels removed and replaced on the Multipurpose Room
  • Covered walkway roof near the Library
  • Possible HVAC updates in Buildings C, D, E, F, and Student Services

The Cove School

  • Perimeter fencing and gates, replacing chain-link, plus new fencing in select locations
  • Turf replaced throughout campus
  • New accessible play structures
  • Under consideration: sport court renovation near the back parking lot

Preliminary cost estimates are in the Measure D Program Update presented to the Board on November 18, 2026.

Upcoming milestones

  • December 4, 2026: Lease-leaseback and construction management proposals due
  • January 2027: Phase 1 projects submitted to DSA
  • January 19, 2027: Board considers the lease-leaseback contract
  • February 10, 2027: Board considers the construction management contract
  • Summer 2027: Fencing and first projects at all three schools
  • 2028: Hall turf and field lighting; HVAC in 2028 or 2029

Campus Fencing

Fencing is one of the first Measure D projects. It grew out of the District's School Safety Task Force, which studied whether to add fencing at each school to balance safety, accessibility, and connection to our community.

  • 2023 to 2024: Hanover Research (Best Practices for Physical Safety and a School Safety Perceptions Study) and Keenan (Threat and Physical Security Assessment and School Climate and Culture Assessment) studies guided the work.
  • Design: Quattrocchi Kwok Architects (QKA) developed fencing and gate options for The Cove, Neil Cummins, and Hall.
  • May 2025: Community feedback sessions at all three schools, plus about 200 responses to an online survey.
  • Summer 2025: Hanover Research study on perimeter security best practices for K-8 schools.
  • August and September 2025: Presentations to the Larkspur City Council and the Corte Madera Town Council.
  • June 2026: Voters approved Measure D, which funds campus fencing as one of the first projects.
  • Fall 2026: The District selected architects to update the designs: MODUS Studios for Hall, and MOTIVE Studios for Neil Cummins and The Cove. The Board of Trustees approved their contracts on November 18, 2026.
  • Updated scope: New 6-foot ornamental fencing and gates at all three schools, with vehicle and pedestrian gates designed for daily drop-off, community use, and emergency access. Hall's project also includes new athletic field turf and field lighting, planned for 2028.
  • November 17, 2026: Campus Fencing Community Meeting at the Hall Middle School Library, where families reviewed the updated designs and shared input.
  • What's next: Phase 1 projects go to DSA in January 2027, and the Board considers the lease-leaseback contract on January 19, 2027. Fencing construction is planned for summer 2027, with the goal of finishing before students return in fall 2027. Hall turf and field lighting follow in 2028.

Fencing documents:

Project Fact Sheets: Coming Soon